Work at Lezayre Road in Ramsey to start next year

Thursday, 29 September 2016

Work to reconstruct the highway and install new water and drainage systems at Lezayre Road in Ramsey has been postponed until next year.

The decision was taken following a constructive meeting on Wednesday evening between the Department of Infrastructure and a range of local stakeholders.

Work originally started on Monday 26 September. In response to local requests to keep the road open, the Department had tried to work with traffic lights in operation.

However, it quickly became apparent that there was insufficient space to operate the site and maintain public safety.

Wednesday’s meeting brought together local representatives including the town’s two MHKs, Ramsey Town Commissioners, the schools, the police, the Chamber of Commerce and the business community.

The meeting agreed that the work could not take place without the road being closed for a period of time. It was also accepted that a compromise would be required and that all parties would work proactively to help the Department prepare its plans for the future road closure.

Jim Davidson, Project Co-ordinator at the Department of Infrastructure, said:

‘The Department was asked to try to keep the road open while the work at Lezayre Road was carried out, but it soon became clear that this was not safe. Public safety is of paramount importance. Last night’s meeting was very positive and there was a shared sense that all parties needed to work together over the coming months to mitigate the effects of the road closure when it comes. A working group will be set up to help review and refine the Department’s closure plans, as everyone accepts there is no easy solution to this matter.’