Maine Road, Port Erin

This project consists of the reconstruction of the Maine Road, form the junction with the Upper Promenade to Maine Avenue, a distance of approximately 180 metres. 

This road is currently unmade and is in the process of being adopted. 

Maine Road, Port Erin

The carriageway reconstruction consists of removable of granular fill, and relaying of a granular sub-base, and 240mm of bituminous material in three layers.  The scheme will involve installation of a drainage system and renewal of services. The scheme will also provide footpaths and parking areas.

The finished scheme will provide a road with a design life of 40 years and which is capable of meeting traffic requirements throughout its proposed life span.

JCK Ltd have been awarded the contract to deliver the work which will take 12 weeks to complete.